Performance Summary Report Definition
Permissions/Access |
Dynamic? |
|
Performance Summary |
Access to the Performance Summary Analysis Tool requires the Permission: View Task Financials and/or View Contract Financials |
N/A |
Contract |
Contract is based on Permission: View Contract Financials |
N/A |
CLIN |
CLIN is based on Permission: View Contract Financials |
N/A |
ROLE |
Role is based on Permission: View Contract Financials |
N/A |
Task/Subtask |
Task/Subtask is based on Permission: View Task Financials and Task Membership |
N/A |
Task Group |
Task Group is based on Permission: View Task Financials and Task Group Membership |
N/A |
Acronyms and Definitions |
|
|
Plan |
Most recently approved Plan data. Plan values are bi-lateral agreements between the NASA Customer and the Contractor |
N/A |
Actuals |
Actual Costs incurred. |
N/A |
ETC |
Estimate to Completion. Also known as Forecast. This is the latest estimate of costs expected and can differ from the Plan. |
N/A |
EAC |
Estimate at Completion of Project. Calculated by adding ITD Actuals and ETC for the balance of Period of Performance. |
N/A |
ITD |
Incurred To Date and/or Inception to Date. |
N/A |
Performance Summary |
|
|
Approved Plan Value |
Total Approved Plan Value |
NO |
Total Funding |
Obligated Funds + Pending Funding (See descriptions of these below) |
NO |
Actual Cost |
Total Actual Cost Inception to Date |
NO |
Total Funding Remaining |
Total Funding(Obligated Funds + Pending Funding) - Actual Cost |
NO |
Estimate at Completion (EAC) |
Total Cost estimated at completion of period of performance. Calculation: Actuals (for Months prior to Selected Month) + Forecasted Value (for Selected & Future Months) ***Forecast Values are based on either Plan or ETC Estimates. Plan or ETC selected based on the most recent Estimate Effective Date. |
YES |
Period of Performance |
Start and End Date for Subject Work as defined in the iSite Task Property |
NO |
Funding Level |
Level Funding is applied (Task or Subtask) |
NO |
Historical Burn Rate |
Calculation: (Actuals from inception thru Last Closed Financial Month)/(Sum of Working Days from Inception thru Last Closed Financial Month) |
YES |
Forecasted Burn Rate |
Calculation: (First Open Financial Month & Future Months Forecast) \ (Sum of Working Days for First Open financial Month & Future Months) |
YES |
Baseline Plan Funding Requirements |
|
|
Estimate At Completion (EAC) |
Total Cost estimated at completion of period of performance. Calculation: Actuals (for Months prior to Selected Month) + Forecasted Value (for Selected & Future Months) ***Forecast Values are based on either Plan or ETC Estimates. Plan or ETC selected based on the most recent Estimate Effective Date. |
YES |
Approved Plan Value |
Total Value from the Time Phased Baseline Plan Table |
NO |
Obligated Funds |
Sum of Obligated Funding. Does not include Funding in statuses Applying Funding, Awaiting Purchase Request, Awaiting Purchase Order. |
NO |
Pending Funding |
Sum of Funding submitted in iSite but not yet Obligated or Published. This includes status of "Funding Awaiting Review", "Awaiting Purchase Request" and "Awaiting Purchase Order" |
NO |
Total Funding |
Obligated Funds + Pending Funding |
NO |
Additional Funding Required to Complete |
Estimate At Completion (Based on Selected Month) - Total Funding |
YES |
Obligated Funding Run-Out Date |
Approximate date Obligated Funds will be expended. Calculation: Where the EAC and Obligated Funds Intersect on the Performance Graph (line not displayed). *** If the Funding Run-Out Date is outside the 12 Months displayed, an approximate Month/Year will be provided. |
YES |
Total Funding Run-Out Date |
Approximate date Total Funds (Obligated + Pending) will be expended. Calculation: Where the EAC and Total Funding Intersect on the Performance Graph. *** If the Funding Run-Out Date is outside the 12 Months displayed, an approximate Month/Year will be provided. |
YES |
Funding Run-Out Date Logic |
A) IF: Total Funding is > EAC, THEN: "EAC Fully Funded" B) IF: Total Funding is 0, THEN: "No Funding" C) IF: EAC is > Funding in within the 12 Months displayed, THEN: Use the latest date of occurrence D) IF: 1) Total Funding is < Total EAC, & 2)Funding is > EAC for the 12 Months Displayed, THEN: 1) Calculate "Remaining Work Days": (Total Funding - Actuals thru selected Month -1)/Forcasted Burn Rate, 2)Use Cumulative Work Days by Month from Financial Month Calendar starting at the Selected Month. When Future Cumulative Workdays for a month is > "Remaining Work Days" Report this Month as the Funding Run Out Date. E) IF: EAC is > Funding for all 12 Months Displayed, THEN: Display the the Greatest Month where (Funding is > than EAC), +1 Month |
YES |
Performance |
|
|
Total Funding |
Cumulative Total Funding by Month |
YES |
Baseline Plan |
Cumulative Baseline Plan by Month |
YES |
EAC |
Estimate at Completion of Month |
YES |
ITD Actual Cost |
Cumulative Actual Cost by Month |
YES |
*Total Funding Run-Out Date |
Projected Date when Costs will equal Total Funding. This is where EAC intersects Funding. |
YES |
***Note: |
Month points on graph represent end of month. |
N/A |
Cumulative Summary |
|
|
Total Funding |
Obligated Funds + Pending Funding (Will only show breakout if user has funding permissions and Pending Funding option selected in report options.) |
YES |
Baseline Plan |
Cumulative Baseline Plan by Month |
YES |
EAC |
Estimate at Completion of Month |
YES |
ITD Actual Cost |
Cumulative Actual Cost by Month |
YES |
*Dynamic? - Indicates if values represented are dynamic based on month selection. |
|
* Exact Date is shown if report Run-Out date is contained within report display range. If not, the Month / Year will only be displayed.